March Move-in For New City Hall

January 22, 2009

From Hans Loewig, CAO

I’m pleased to be in touch with good news this morning about the completion of City Hall and our move-in schedule.

Resulting from a thorough inventory of work that remained after Urbacon’s termination, the City’s general contractor estimates that City Hall will be substantially complete by the end of March 2009.  Departmental move-ins are being scheduled to take place even earlier in mid-March.

A report containing these details will be presented to Council next Monday night.